The following schematic shows the work packages of the project and the interaction between them and the users and stakeholders.
WP Schedule
The project kick-off was in Feb. 2021. The Final Review is planned to take place in Feb. 2023. Below you can find the planned timings of the WPs.
WP1 Requirements Consolidation: Feb. 2021 – May 2021 (closed, see the deliverables below)
WP2 Service Chain Specification: May 2021 – Sep. 2021 (closed, see the deliverables below)
WP3 Service Chain Implementation and Testing: Sep. 2021 – Mar. 2022
WP4 Service Delivery: Apr. 2022 – Oct. 2022 (ongoing)
WP5 Service Uptake and Utility Assessment: Jul. 2022 – Feb. 2023
Baltic Workshop during Oct 2022
WP6 Management: Feb. 2021 – Feb. 2023
The deliverable documents and other results of the project will be available through the links in the table below once approved by ESA.
PM =Progress Meeting, PDR = Preliminary Design Review, SRR = System Readiness Review, SOR = Service Operations Review, FR = Final Review.